Seems that Cincinnati has
resolved some utility and costs issues:
City & Duke Energy Reach Streetcar Agreement
Duke Energy To Begin Moving Its Utilities
Today, Mayor Mark Mallory and City Manager Milton Dohoney, Jr.
announced that the City of Cincinnati and Duke Energy have reached an
agreement on the Streetcar project. Under the agreement, Duke Energy
will begin moving its utilities now, while a court determines
responsibility for the relocation costs later.
The City and Duke have also agreed to an operations plan for how Duke
and the City will work in partnership once the Streetcar is
operational.
And
Milwaukee is making some progress, though right now it looks like Cincinnati will get there first:
The city plans to release the proposed route of the Milwaukee
streetcar project by late spring or early summer, and hopes to begin
construction of the streetcar guideway in spring 2014.
The schedule was included in a filing with the state's Public Service
Commission. The PSC has not yet ruled on whether the city or utilities
must pay for moving utility lines out of the way of the streetcar route,
a cost utilities have estimated at more than $55 million.